Framework Procurement Timetable
We have identified below key dates in the procurement timetable. An OJEU restricted procedure will be used to procure the framework.
| Item | Timing |
| Launch Workshop | E.April 2008 |
| Visits to potential users for data gathering / clarification | M.April to M.May |
| Initial Specifying of Frameworks mode of Operation | M.May to M.June |
| Contractor Consultation | E.July |
| Consultant / Designer Consultation | E.July |
| Framework User Consultation | E.July |
| Users Indicative Intentions to Use Framework | L.July to L.Aug |
| Contractor’s Complete Pre Qualification Questions | E.Sept to L.Sept |
| Contractor’s Completion of Intention to Tender | L.Nov to M.Jan 2009 |
| Contractor’s notified of Award of Contract | TBC |
| Mobilisation Period | TBC |
| Contractor’s Briefed on Use of Framework | TBC |
| Framework Users Briefed on Use of Framework (including Consultants / Designers ) |
TBC |
| Framework Initiated | TBC |